MNDOT State Project No. 2751-58 Basset Creek

Project Owner

MNDOT

Project Year

2018

Location

Minneapolis, MN

The scope of this project was to remove 176 LF of existing 12’ x 16’ Basset Creek tunnel that has an existing MCES sanitary sewer under it. We then slip lined 230 LF of 60” FRP in the existing MCES line. To complete this work, Minger had to set up temporary conveyance in order to slip line the exiting sanitary sewer.